Archdiocese of Mbarara Development Association Member registration
Home/Our work/Rubaga project

The Rubaga Construction Project

The home of AMDA. A multipurpose hall, offices for AMDA, ABF and the SACCO, a canteen and a four-level, 15-bedroom clergy residence on land owned by the Archdiocese of Mbarara.

2015The year the project began
UGX 5.1bnInitial budget for the complex
24 Nov 2024Main hall first used for Mass and meetings
UGX 936MEstimated total still required

What we are building

Once complete, the complex will be a source of income to run AMDA activities and take care of the seven pillars.

Multipurpose hall

The main hall, in use since 24 November 2024 for Mass and meetings, though still unfinished.

Offices

Office space for AMDA, the Bereavement Fund (ABF) and the SACCO.

Clergy residence

Four levels, 15 bedrooms. The ground and first floors are complete and occupied.

Canteen

A cafeteria for members and visitors, with ceiling and wiring works done.

Status as of 25 March 2026

This summary comes from the Construction Committee's update of 30 March 2026, signed by Eng. Anthony Rucukye, Chairperson of the Construction Committee.

  • The ground and first floors of the clergy residence are complete and occupied.
  • The second and third floors, including the Archbishop's suite, are incomplete and uninhabitable.
  • The main hall is unfinished but in use since 24 November 2024.
  • A UGX 200 million loan was secured from the AMDA SACCO in August 2024 at 17% interest a year to speed up partial occupation.
Loan repayment, as of 25 March 2026
UGX 150,376,850

paid so far. The outstanding balance is UGX 47,570,950.

About 76% of the loan and interest has been repaid. The plan was to clear the balance by September 2026.

Works completed since November 2024

  1. Timber tiling of the Archbishop's suite (3rd floor)
  2. A 2-bedroom guard house, with water, electricity, tiling and fittings
  3. First-fix electrical wiring for the main hall, cafeteria and office spaces
  4. Plastering of the main hall
  5. First coat of paint in the main hall
  6. Floor screeding of the main hall
  7. Ceiling works for the cafeteria and office spaces
  8. Steel balustrades for safety

What is still needed

ItemEstimate (UGX)
A. Clergy house: windows, glazing, painting, tiling, doors, wiring, plumbing211,826,000
B. Main hall: windows, balustrades, doors, tiling, painting, plastering, wiring, piping547,498,000
C. External works: landscaping, paving, lighting, utilities, fencing, drainage129,332,000
D. Loan balance (principal and interest)47,570,950
Grand total required936,226,950

Where the money would go

Main hallUGX 547,498,000
Clergy houseUGX 211,826,000
External works and utilitiesUGX 129,332,000
Loan balanceUGX 47,570,950

Our journey so far

  1. 2015: Construction begins

    AMDA starts on the Archdiocese's land at Rubaga after an agreement of undertaking from the Mother Archdiocese.

  2. August 2024: SACCO loan

    UGX 200 million is secured to fast-track partial occupation of the clergy residence.

  3. 24 November 2024: "Tutaahe Rubaga" fundraiser

    The main hall is used for the first time, for Mass and the fundraiser, led by the Archbishop of Mbarara.

  4. 25 March 2026: Update

    Loan repayments total UGX 150,376,850 and works continue on the hall and cafeteria.

  5. September 2026: Target

    Clear the outstanding loan, then resume full construction.

Our appeal

Only 46% of pledges made at the "Tutaahe Rubaga" fundraiser have been fulfilled.

If every monthly animation raises UGX 10 million, the loan can be cleared comfortably. The Committee asks everyone who made a pledge on 24 November 2024 to honour it.

Special thanks to Hon. Kobusingye Adrine, Chairperson of the NRM Women League, Kyamuhunga Parish, who offered to fund windows and doors for the main hall, and to all members who have given.

How you can give

Every contribution, big or small, brings the building closer to completion.

Honour your pledge or give

Contact the Construction Committee or the AMDA office for payment details.

Make a pledge

Give materials

Windows, doors, tiles, paint and fittings are needed for the hall and clergy house.

Offer materials

Give your skills

Engineers, surveyors, accountants and project managers can volunteer time and expertise.

Volunteer

Animate a Monthly Mass

Parishes and groups that animate the Monthly Mass raise funds for the project.

See events

Photo updates

Rubaga construction project
The Rubaga complex
Tutaahe Rubaga fundraiser
Members at the Tutaahe Rubaga fundraiser
Partners and supporters
Partners and supporters

Who leads the project

The Construction Committee is chaired by Eng. Anthony Rucukye. The first committee was headed by Eng. Dr. Silver Mugisha, Managing Director of the National Water and Sewerage Corporation, and it was later led by Mr. Giles Germany Aijukwe, CEO of Letshego.

Meet the AMDA leaders

Help us finish the home of AMDA

Turibamwe, omuri Kristo! Together, in Christ.

How to give

Mass times and directions

Monthly AMDA Mass

When
The last Sunday of every month, except December
Time
10:00 am
Language
Runyakitara
Where
AMDA House, Rubaga, Kampala
Animated by
A parish, school or council each month

AMDA House

Plus code
8G5X+F5V, Kampala
Phone
+256 772 412 619
Get directions